Research: Multiskilling Can Shorten Construction Schedules by Up to 38%

New research conducted by the Simplar Foundation reveals that multiskilling can shorten construction schedules by up to 38%, offering a promising strategy to help address America’s skilled labor shortage. By expanding workers’ skills and improving workforce flexibility, contractors can increase their capacity to meet growing construction demands without relying solely on an already-constrained labor market, according to Associated Builders and Contractors’ analysis of the research.

The research marks the final report in its three-part multiskilling series. Together, the studies provide compelling evidence of how multiskilling can improve workforce utilization, increase productivity and strengthen project delivery while creating greater opportunities for construction craft professionals.

The report, Schedule Duration and Labor-Curve Outcomes Associated with a Multiskilled Labor Strategy, analyzed nearly 90,000 labor hours across 18 construction projects involving 11 contractors. Researchers examined actual project labor records to evaluate how multiskilled workers helped contractors match available skills to changing project needs, maintain workflow continuity and manage daily staffing demands.

Key findings include:

  • Shorter project schedules: Multiskilled crews completed work in approximately 22% to 38% fewer workdays than a modeled single-trade labor strategy was estimated to require. Conversely, restricting workers to one trade required 28% to 62% more workdays to accomplish the same work.
  • Improved workforce availability: On most project days (73%), relying on single-trade staffing would have left at least one trade without sufficient available labor compared to multiskilled crews.
  • Greater staffing flexibility: A single-trade strategy required more than one-third additional staffing on the busiest project days, underscoring the value of workers with multiple skills who can adapt to changing project needs.
  • Broader worker capabilities: Researchers documented 80 unique trade and skill combinations across 18 trades. Multiskilled workers performed an average of 3.2 different trades or skills over the course of their projects.

For more details, click here.

To explore the full research series, visit simplarfoundation.org/multiskilling. To learn more about ABC’s workforce productivity initiatives, visit abc.org/multiskilling.