Works have now commenced on Plot 3 of the mixed-use industrial scheme, Matrix 49, in Avonmouth, Bristol (United Kingdom).
Delivered by McLaren Construction (Midlands and North), on behalf of clients BGO Wire PropCo Ltd and Equation Properties, the £21.6-million, 13-acre plot will be situated on the 65-acre site of Matrix 49, continuing the transformation of the site into industrial, logistics and office space in a prime location next to the M49 motorway and mainline railway line to the north.
Once complete, the units and office space will provide future clients with sustainable premises, for businesses working toward net-zero targets.
Planned works include procuring the infrastructure and warehouse unit, together with a 219,660-square-foot warehouse alongside the construction of 11,365 square feet of office space, a control tower and a gatehouse. The project also includes associated external works, hard standings, car, HGV and motorcycle parking with over 200 spaces, road landscaping, loading docks, level access and drainage.
Key complex aspects of the build include a rhine diversion and a suspended ground floor slab. Archaeological investigation works have now completed on Plot 3, as have clearance works to remove existing topsoil and vegetation, infill and divert existing rhines, and import clean, inert and tested material to the site, which were laid in layers to raise the existing levels.
Construction is expected to take 42 weeks in total and, once complete, Plot 3 is on target to achieve a BREEAM Excellent rating. The contractor has been working closely with the ecological site team to ensure the protection of the water vole population, which have been located in the Redwick Common and Cranmoor Rhines.