Hospital in England Completes, Opens in Less than 3 Weeks to Respond to Pandemic

Less than three weeks since BAM Construction and its partners began construction, NHS Nightingale Yorkshire and the Humber opened. Based in Harrogate Convention Centre, located in England, it will provide approximately 500 additional beds for coronavirus patients, if local services need them. The new facility is one of seven Nightingale hospitals to be set up around the country as part of a massive NHS effort to respond to the greatest global health emergency in more than a century. This extra capacity is on top of the 33,000 additional beds freed up across NHS hospitals – the equivalent of building 50 … Read more

Filed under: Around the World, eNewsTagged with: , , ,

Glasgow’s Scottish Events Campus Transforms into NHS Louisa Jordan Hospital

Balfour Beatty recently completed the new temporary NHS Scotland Hospital, NHS Louisa Jordan, at Glasgow’s Scottish Events Campus, on behalf of the Scottish Government. Acting as principal contractor, Balfour Beatty completed construction, along with its local supply chain and partner contractors, in just 20 days. The clinical facility, which has been constructed to provide extra patient capacity, will provide 1,036 beds for COVID-19 patients, should NHS Scotland require additional flexibility during the pandemic. Construction included the building of sterile temporary wards, installing and commissioning life-saving oxygen and gas systems, as well as laying 23,000 square meters of vinyl flooring. Balfour … Read more

Filed under: Around the World, eNewsTagged with: , , ,

U.S. Army Corps of Engineers, Holt Construction Collaborate to Build Temporary Hospital

Together with the U.S. Army Corps of Engineers, Bergen County and FEMA, Holt Construction completed a temporary hospital in just two weeks at Bergen New Bridge Medical Center in Paramus, New Jersey. The two fully equipped tents, the first of its kind for Army Corps temporary facility construction standards, will serve as a treatment facility for acute, non-COVID-related patients due to the influx of COVID-positive patients in the main building. The temporary hospital will serve an additional 100 patients total and is located in a large parking lot adjacent to BNBMC’s main building with a covered walkway linking the two … Read more

Filed under: ProjectsTagged with: , , , ,

450-Bed Miami Beach Convention Field Hospital Completed in Response to Coronavirus Pandemic

A 450-bed hospital, built inside the Miami Beach Convention Center located in Miami Beach, Florida, was completed more than a full day ahead of a very aggressive two-week schedule, ensuring the facility is ready, if needed, before the anticipated peak of COVID-19 in South Florida. The temporary hospital is a state and federal partnership in response to the Coronavirus pandemic. The Army Corps of Engineers selected Robins & Morton to perform the work. The general contractor engaged more than 20 trade contractors from South Florida, as well as RLF Architects for project design and engineering. More than 250 people worked … Read more

Filed under: eNews, ProjectsTagged with: ,

Mid-Century Buildings Renovated into Temporary Healthcare Facilities in California

Electrical contracting firm Rosendin joined the coronavirus crisis response efforts to help communities care for sick patients. The company recently completed renovations to transition two mid-century buildings into temporary healthcare facilities in California and expects to be called into action for similar projects in the coming weeks. Turner Construction contacted Rosendin for the rapid-response project in Indio to convert two buildings on the city’s fairgrounds into medical centers for people suspected of having COVID-19. Less than 24 hours after getting the call, Rosendin’s special projects team were onsite. In less than three days, the Fullenwider Auditorium and the Taj Mahal … Read more